Restoration Projects

Top-down and Bottom-up Processes Quarterly Tasks

2005 Quarterly Project Tasks:

1st Quarter Tasks (October 1, 2004 - December 31, 2004)
Status: Complete

Tasks to be performed:

October: Field work (pps, ctds, fish surveys) Dec. 31: Finish lab analysis

Progress report:

Update from Project Manager (2/11/05): Completed. Some lab work continuing

2nd Quarter Tasks (January 1, 2005 - March 31, 2005)
Status: Incomplete

Tasks to be performed:

January: Annual GEM workshop Mar 20-30: Field work (pps, stds, fish surveys)

Progress report:

(Not Available)

3rd Quarter Tasks (April 1, 2005 - June 30, 2005)
Status: Incomplete

Tasks to be performed:

April 15-June 30: Field work (benthic & sediment cores, pps, ctds, fish surveys, experiments)

Progress report:

(Not Available)

4th Quarter Tasks (July 1, 2005 - September 30, 2005)
Status: Incomplete

Tasks to be performed:

July 1-Sep 30: Field work (benthic & sediment cores, pps, ctds, fish surveys, experiments) Sep 1: Submit annual report o EVOS and submit manuscript

Progress report:

(Not Available)

Can't find it? We can help.

We're working to make all of our project information available online. Currently, we have 380 Final Reports and 811 Annual Reports available for download. If you would like more information on any project you find using this search engine, please contact us. We can search our files for the information you request.

Or, check with ARLIS.

The Alaska Resources Library and Information Service (ARLIS), located on the UAA campus, may have the document you need.

Phone: (907) 272-7547

reference@arlis.org

http://www.arlis.org/