Restoration Projects

Status of Subsistence Uses Quarterly Tasks

2005 Quarterly Project Tasks:

1st Quarter Tasks (October 1, 2004 - December 31, 2004)
Status: Rescheduled

Tasks to be performed:

FY05, 1st Quarter (October 1, 2004 – December 31, 2004) October & November 2004 Prepare review draft of final report December 2004 Draft report distributed for review

Progress report:

Update from Project Manager (2/8/05): This project continues to be essentially on track in conformance with the revised schedule submitted in the first quarterly report, with the minor exceptions noted below. Data analysis is still underway due to problems with reporting of harvest data from Karluk. Inetrnal draft finalreport distribution has been postponed until March. Note: Project Manager shows tasks for Oct.-Nov. as "Complete preliminary datan analysis and conduct data review workshop"

2nd Quarter Tasks (January 1, 2005 - March 31, 2005)
Status: Complete

Tasks to be performed:

FY05, 2nd Quarter (January 1, 2005 – March 31, 2005) January 2005 Report findings at Marine Science Symposium March 15, 2005 Circulate internal review draft of final report; underway NOTE: On April 6, we received approval from executive director Phillips of an extension request moving the final report due date from April 15 to June 30. I have revised the attached list of milestones and schedule to reflect this change.

Progress report:

The key project goal for this quarter was submission of a review draft of the final report by June 30, 2005. Extension of the due date for this review draft from April 15 to June 30 had been approved by executive director Gail Phillips on April 6. We completed the review draft on June 30. As per instructions from the Trustee Council’s Science Coordinator, Richard Dworsky, we delivered three paper copies and one electronic copy (in Microsoft Word format) to Dr. Dworsky on July 1. It is our understanding that he will handle the peer review of the report.

3rd Quarter Tasks (April 1, 2005 - June 30, 2005)
Status: Complete

Tasks to be performed:

FY05, 3nd Quarter (April 1, 2005 – June 30, 2005) June 30, 2005 Submit draft final report to EVOS TC (change from 4/05) Submit data to EVOS TC Data Archive (postponed from March 2005) September 30, 2005 Mail project summary (postponed from 4/05) NOTE: On April 6, we received approval from executive director Phillips of an extension request moving the final report due date from April 15 to June 30. I have revised the attached list of milestones and schedule to reflect this change.

Progress report:

Draft final submitted.

4th Quarter Tasks (July 1, 2005 - September 30, 2005)
Status: Incomplete

Tasks to be performed:

(Not Available)

Progress report:

(Not Available)

Can't find it? We can help.

We're working to make all of our project information available online. Currently, we have 380 Final Reports and 811 Annual Reports available for download. If you would like more information on any project you find using this search engine, please contact us. We can search our files for the information you request.

Or, check with ARLIS.

The Alaska Resources Library and Information Service (ARLIS), located on the UAA campus, may have the document you need.

Phone: (907) 272-7547

reference@arlis.org

http://www.arlis.org/